REMOVE POWERPLANT
(Continued)
4-10
21.
Remove engine transmission (16) from
powerplant (1) (Task 6-100).
REMOVE POWERPLANT WITH ENGINE
TRANSMISSION REMOVED
NOTE
Art for steps 22 and 24 is referenced
to remove powerplant with engine
transmission installed section.
Referenced art shows engine
transmission installed but will not
affect task performance.
22.
Perform steps 1 thru 5 and 8. Go to step 23.
23.
Install sling (20) as follows:
a.
Open access door (21) in engine access
cover (22).
b.
Connect two cables (23) to forward fittings
(24) on powerplant (1).
c.
Connect cable (25) into aft fitting (26) through
cover (22).
d.
Adjust sling (20) until eye (27) is over aft hole
(49) in sling bar (29).
24.
Perform steps 10 thru 20. Go to Follow-On
Maintenance.
FOLLOW-ON MAINTENANCE:
Record any accumulated Emergency Power Time in
DA Form 2408-15.
Perform AT TIME OF ENGINE REMOVAL FOR ANY
REASON inspection (Task 1-92).
END OF TASK
4-51