TM 55-1520-240-23-9
11-6.3
ISOLATION PROCEDURES FOR CHECKING CONTROLS LOOSENESS
(Continued)
11-6.3
50.
Working through right landing light access (69),
check six connecting links (70 thru 75) for loose
swaged inserts (Tasks 11-7 and 11-7.1) and
loose rod end bearings (Task 11-9).
51.
Check link (76) for loose bearing (Task 11-9).
52.
Working through left landing light access (77),
check eight connecting links (78 thru 85) for
loose swaged inserts (Tasks 11-7 and 11-7.1)
and loose rod end bearings (Task 11-9).
53.
Check link (86) for loose bearing (Task 11-9).
11-34