TM 55-1520-240-23-3
4-13
INSTALL POWERPLANT
(Continued)
4-13
2.
Install sling (3) as follows:
a.
Open access door (4) in engine access cover
(5).
b.
Connect two cables (6) into forward fittings
(7) on powerplant (2).
c.
Connect cable (8) into aft fitting (9) through
cover (5).
d.
Adjust sling (3) until eye (10) is over center
hole (11) in sling bar (12).
e.
Install pin (13) through bar (12).
3.
Connect hoist (14) to eye (10) of sling (3). Absorb
weight of powerplant (2) with hoist.
4.
Remove pin (15) from adapter fitting (16) and
aft mount link (17).
Powerplant is heavy and can injure
personnel if it drops. Personnel must
stay clear while powerplant is being
moved by hoist.
5.
Loosen four bolts (18) on trailer adapter (T19)
(19) and push down to side.
6.
Install rope guide lines (20).
4-109