TM 55-1520-240-23-3
4-12
ASSEMBLE POWERPLANT
(Continued)
4-12
48.
Position two hoses (67 and 68) on powerplant (1).
49.
On No. 2 powerplant, install four clamps (69)
and install two screws (70). Install two nuts (71)
on screws. Remove tag and tape from hoses
(67 and 68).
50.
On No. 1 powerplant, install four clamps (72)
on two hoses (67 and 68). Install three screws
(73), spacer (74), washer (75), and two nuts (76).
Remove tag and tape from hoses.
51.
Connect hose (77) to elbow (78) on fuel control
(79). Remove tag.
52.
Install two clamps (80) and install screw (81) and
nut (82). Remove tape from hose (77).