TM 55-1520-240-23-9
11-84
INSTALL STICK PITCH POSITION INDICATOR
(Continued)
11-84
12.
Working through access (37), slide tube (39)
forward until about 1 inch of cable (12) shows
from end of tube.
13.
Install collet (43) on cable (12), about 0.4 inch
from end of cable. Turn clockwise.
14.
Pull tube (39) aft until collet bottoms in tube.
15.
Install bearing (44) in tube (39) until bottomed.
Turn clockwise.
16.
Check bearing (44). Move bearing fully forward
and fully aft using dial indicating scale (45).
Force required to move bearing shall be less
than 1 pound.
17.
Move bellcrank arm (46) forward and slide tube
(39) aft. Align bearing (44) with hole (47) in arm.
18.
Position washer (48) between bearing (44) and
arm (46). Install bolt (49), two washers (50 and
51) and nut (52). Do not tighten nut at this time.
19.
Rig stick position indicator (Task 11-45).
11-444