TM 55-1520-240-23-7
9-34
INSTALL APU GENERATOR
(Continued)
9-34
6.
Remove tape and connect three wires (10) to
terminals (11) by installing three washers (12)
and nuts (13). Remove tags.
7.
Install terminal cover (14) and tighten two
fasteners (15).
8.
Remove tape and connect four wires (16) to
terminals (17) by installing four washers (18) and
nuts (19). Remove tags. Install terminal cover
(20) and tighten two fasteners (21).
NOTE
Ensure APU generator wires are
properly connected to the APU
generator as the APU generator
manufacturers (Lucas and Leland)
have different wire terminal
attachment points.
NOTE
If Leland APU generator is installed,
Lucas generator terminal board will
not fit. Use rubber nipple (P/N MS
25171-4S - NSN 5975-00-553-7077)
or equivalent.
9.
Remove tape and connect six wires (22) to
terminals (23) by installing six washers (24) and
nuts (25). Remove tags. Install terminal cover
(26) and tighten two fasteners (27).
INSPECT
FOLLOW-ON MAINTENANCE:
Perform operational check of generator (TM
55-1520-240-T).
Install APU drip pan (Task 2-3).
Fold auxiliary loading ramp (TM 55-1520-240-10).
Close cargo ramp (Task 2-2).
END OF TASK
9-110