TM 55-1520-240-23-3
4-107
INSTALL NO. 1 OR NO. 2 GAS PRODUCER CONTROL BOX
4-107
INITIAL SETUP
Applicable Configurations:
Without 74
Tools:
Aircraft Mechanics Tool Kit, NSN 5180-00-323-4692
Materials:
None
Personnel Required:
Aircraft Electrician
References:
TM 55-1520-240-23P
NOTE
Procedure is same to install No. 1
or No. 2 gas producer control box.
Installation of No. 1 control box is
shown here.
1.
Position box (1) on fuselage (2).
2.
Install four screws (3) and washers (4).
3.
Connect two electrical connectors (5 and 6).
Remove tags.
FOLLOW-ON MAINTENANCE:
Perform operational check of gas producer system
(TM 55-1520-240-T).
Close No. 1 gas producer control box access panel
(Task 2-2) or No. 2 gas producer control box
access panel (Task 2-2).
END OF TASK
4-391