TM 55-1520-240-23-9
11-194
REMOVE FORWARD RIGHT OR LEFT CONNECTING LINKS
(Continued)
11-194
NOTE
Attaching bolts, washers, and nuts
will be temporarily installed after links
are removed.
Procedure is same to remove forward
left or right connecting links. Left
connecting is shown here.
NOTE
If a crack in the connecting links
or bellcranks is suspected during
removal, refer to TM 1-1520-253-23.
1.
Working from forward left work platform, remove
cotter pin (1), nut (2), two washers (3), and bolt
(4) from bellcrank (5). Disconnect link (6) from
bellcrank.
2.
Install bolt (4), two washers (3), and nut (2)
loosely in bellcrank (5).
3.
Move bellcrank (7) aft. Remove cotter pin (8),
nut (9), two washers (10), and bolt (11) from
bellcrank (7). Remove connecting link (6) from
bellcrank.
4.
Install bolt (11), two washers (10), and nut (9)
loosely in bellcrank (7).
FOLLOW-ON MAINTENANCE:
None
END OF TASK
11-792