TM 55-1520-240-23-7
9-98
INSTALL OVERHEAD PANEL
(Continued)
9-98
3.
Connect ground wire (10) to structure (11). Install
screw (12), three washers (13), and nut (14).
4.
Remove tape and install wire (15) on terminal
(16) using washer (17) and nut (18). Remove tag.
5.
Remove tape and install two wires (19) on
terminal (20) using washer (21) and nut (22).
Remove tag.
6.
Connect connector (23) to receptacle (24).
Remove tag.
7.
Connect connector (25) to receptacle (26).
Remove tag.
8.
Connect connector (27) to receptacle (28).
Remove tag.
9.
Connect connector (29) to receptacle (30).
Remove tag.
10.
Connect connector (31) to receptacle (32).
Remove tag.
11.
Connect connector (33) to receptacle (34).
Remove tag.
12.
Check all wire bundles in the vicinity of the
overhead panel to ensure none are chafed. If
chafing is noted, rewire the bundle. If rewiring
will not correct the chafing, apply spiral wrap,
NSN 9390-00-836-8493 or equivalent, to the
chafed area of the bundle. If the insulation has
been worn away to expose a conductor, replace
affected components.
13.
Pivot panel (1) up. Install two bolts (35).
INSPECT
FOLLOW-ON MAINTENANCE:
Perform operational check (TM 55-1520-240-T).
END OF TASK
9-313