TM 55-1520-240-23-6
7-54.2
INSTALL NO. 1 OR NO. 2 POWER CONTROL MODULE MISCELLANEOUS CHECK
VALVES
(Continued)
7-54.2
NOTE
The pump case drain check valve
installation is shown. Procedure for
installation of the system fill, power
transfer, pump pressure, case drains,
and external power supply check
valves is the same.
1.
Install packing (1) on check valve (2) as follows:
a.
Place packing installation tool (3) (refer to
table) over port end of check valve (2).
b.
Submerge check valve (2) and packing (1) in
hydraulic fluid (E199).
c.
Slide packing (1) over tool (3) onto check
valve (2).
d.
Ensure packing (1) is not twisted and is
properly installed in groove (4). Remove
packing installation tool.
Check Valve
Packing Tool
Combination
Wrench and
Drive Tool
Lockring
Removal Tool
Installation Torque
Inch-Pounds
System Fill
ORT-437
RF9806DW
RF9806LPD
180-245
Case Drain
ORT-562
RF9808DW
RF9808LPD
430-510
Pump Case Drain
ORT-1125
RF9816DW
RW9816LPD
1140-1260
Power Transfer
ORT-687
RF9810DW
RW9810LPD
600-680
Pump Pressure
ORT-437
RF9806DW
RW9806LPD
180-245
External Power Supply
ORT-562
RF9808DW
RW9808LPD
430-510