PREPARE AFT ROTOR SHAFT FOR SHIPMENT OR STORAGE
(Continued)
6-60
10.
Install rotor shaft (6) in shipping container (T1)
(11) as follows:
a.
Inspect and prepare container (11) (TB
55-8100-200-25).
b.
Install hoisting eye (12) in top of shaft (6).
Connect work hoist hook (13) to eye marked
AFT SHAFT.
c.
With aid of helper, lower shaft (6) into
container (T1) (11).
d.
Remove hoisting eye (12) from shaft (6). With
aid of helper, lower shaft into two pads (13).
e.
Install two clamps (14) over shaft (6). Install
six washers (15) and nuts (16).
f.
Prepare required maintenance forms and
records (DA PAM 738-751 and TB 750-126).
g.
Put four 16-unit bags of desiccant (E160) into
container (T1) (11).
h.
Install cover (17) on container (T1) (11).
Install bolt (18), two washers (19), and nut
(20) at 30 places.