TM 55-1520-240-23-10
12-18
INSTALL FIRE PULL CONTROL
(Continued)
12-18
4.
Pull out shaft (1).
5.
Check continuity between terminal (2) and
terminal (5).
6.
Repeat step 5 for each switch (4).
INSTALL CONTROL
7.
Connect eight electrical wires (6) to switches (4).
Install eight screws (7) and washers (8). Remove
tags from wires.
8.
Install packing (9) on control (10).
9.
Install shaft (1) through hole (11) in instrument
panel (12).
10.
Install two screws (13).
11.
Connect warning light electrical wires (14). Use
splice and insulation (E203) to make connection.
Remove tags from wires.
INSTALL FIRE WARNING PANEL
12.
Position fire warning panel (15) on center
instrument panel (12).
13.
Install two screws (16).
14.
Install two panel lights (17).
INSPECT
12-50