TM 55-1520-240-23-5
6-63
INSTALL AFT ROTOR SHAFT THROUGH CABIN
(Continued)
6-63
16.
Connect pressure hose (28) to filter (29).
Connect connector (30) to oil pressure switch
(31).
17.
Remove hook (4) and hoisting eye (6) from top of
shaft (1).
18.
Remove rope guide line (8) from around bottom
of rotor shaft (1).
INSPECT
FOLLOW-ON MAINTENANCE:
Install aft transmission (Task 6-97).
Service aft transmission with oil (Task 1-54).
Install swashplate (Task 5-133).
Install drive arms (Task 5-112).
Install drive collar (Task 5-111).
Install weather-protective cover (Task 5-138).
Install rotary-wing head (Task 5-9).
Check vertical pin angle (Task 11-58).
Install rotary-wing blades (Task 5-84).
Phase rotary-wing system (Task 6-28).
Perform operational check of aft rotor shaft chip
detector (TM 55-1520-240-T).
Close pylon work platforms (Task 2-2).
Perform a ground run (TM 55-1520-240-10).
END OF TASK
6-246