TM 55-1520-240-23-1
1-80
MATERIALS CLEANING
1-80
INITIAL SETUP
Applicable Configurations:
All
Tools:
As Required
Materials:
As Required
Personnel Required:
Structural Repairer
References:
Task 1-76
Task 1-77
Task 1-81
Task 1-82
Task 1-83
1.
This task provides general information for
cleaning all materials used in the construction
of the helicopter.
2.
The following table, along with Tasks 1-76, 1-77,
1-81, 1-82, and 1-83, provides recommended
cleaning solutions.
3.
If the recommended cleaning solutions or
compounds are not available, a cleaning
procedure using approved materials can be used
at the Maintenance Officers discretion. However,
the recommended cleaning procedures should
be used as soon as the materials are available.
1-302