TM 55-1520-240-23-6
7-112
INSTALL NO. 1 OR NO. 2 FLIGHT CONTROL RESERVOIR/COOLER TEMPERATURE
SWITCH
(Continued)
7-112
NOTE
Procedure is same to install No. 1 or
No. 2 flight control reservoir/cooler
temperature switch.
1.
Install switch (1) and packing (2) in port (3).
2.
Connect electrical connector (4) to switch (1).
3.
Lockwire switch (1), bulb (5), and valve (6). Use
lockwire (E231).
INSPECT
FOLLOW-ON MAINTENANCE:
Service reservoir/cooler (Task 1-60, 1-61, or 1-62).
Bleed flight control hydraulic system (Task 7-16).
Perform operational check of flight control system
(TM 55-1520-240-T).
Close right forward access panel (Task 2-2).
Close right forward work platform or left pylon access
panel (Task 2-2).
END OF TASK
7-515