TM 55-1520-240-23-5
6-51
INSTALL FORWARD TRANSMISSION PACKAGE
(Continued)
6-51
FOLLOW-ON MAINTENANCE:
Install forward connecting links (Task 11-195).
Install forward transmission adapter assembly (Task
6-8).
Install No. 1 and No. 2 drive shafts (Tasks 6-17 and
6-18).
Install forward transmission oil cooler air inlet duct
(Task 6-122).
Install forward transmission fairing (Task 2-67 and
2-68).
Install rotary-wing blades (Task 5-84).
Service transmission (Task 1-54).
Perform ground run (TM 55-1520-240-10).
Install forward transmission drip pan (Task 2-3).
Perform neutral rig check (Task 11-33).
Bleed flight control hydraulic system (Task 7-16).
Perform after-maintenance special inspection (Task
1-92).
Check torque on hydraulic pump mounting nuts after
first flight (step 23).
END OF TASK
6-201/(6-202 blank)